UPDATE: Decision time for John Horgan on Site C dam

Energy Minister Michelle Mungall says delaying it is off the table

Premier John Horgan’s cabinet intends to make a decision on whether to continue building the most expensive construction project in B.C. history by the end of 2017.

The B.C. Utilities Commission released its independent report on the project Wednesday, ordered by Horgan to fulfil a promise he has repeated many times since becoming NDP leader.

The BCUC report questions whether Site C can make its 2024 completion date, and concludes the cost “may” exceed $10 billion. It describes the option of suspending work and restarting it in 2024 as the “least attractive of the three scenarios” set out by the government.

Energy Minister Michelle Mungall said Wednesday the report is technical and requires further study, but one thing that is clear is that delaying Site C is not an option that would protect B.C. Hydro ratepayers from unnecessary rate increases.

In the legislature Wednesday, Peace River South MLA Mike Bernier called on the government to make a decision within a month, to provide certainty to the people working at Site C. Eight years of study done under the B.C. Liberal government, and court decisions saying consultation with affected people was adequate, mean no further delay is needed, Bernier said.

Green Party leader Andrew Weaver said the report “should be viewed as the final nail in the coffin of Site C,” due to potential cost overruns and the B.C. Liberal government’s rush to secure fixed-term electricity supply to liquefied natural gas projects.

“The one issue of concern” is the transfer of the $4 billion cost of scrapping Site C to be added to the provincial debt, Weaver said.

Horgan’s government instructed BCUC to come up with cost estimates for completing the dam, pausing construction for a more thorough review of alternatives and future electricity demand, or stopping it and restoring the project area.

The report estimates the cost of shutting down Site C and remediating the project area to be $1.8 billion, plus the cost of finding alternative energy sources to meet demand, on top of the $2 billion already spent.

“The suspension and restart scenario adds at least an additional $3.6 billion to final costs and is by far the most expensive of the three scenarios,” the report states.

The BCUC panel also concluded that “increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Horgan said Tuesday that one more round of consultation with area Indigenous communities will be conducted next by Indigenous Relations Minister Scott Fraser, and then cabinet will consider its options.

B.C. Hydro has already awarded the major contracts for the powerhouse, river diversion and main civil works in the riverbed.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

High speed internet coming to remote CRD areas

Ottawa to invest $34 million to build 3.5 million metres of subsea fibre optic cable in B.C.

Affordable housing organization seeks to build in Sooke

Habitat for Humanity hopes to build cluster of townhouses at 2008 Murray Road

Council re-tenders Murray Road staircase project

Project could be delayed months

Langford loses bid to host Amazon HQ2

Mayor hopes to attract more tech jobs to city

Whooping cough detected in Claremont student

15 Greater Victoria schools have been informed of a student with pertussis since September

WATCH: Giant waves smash Ucluelet’s Amphitrite Point

Folks made their way to Ucluelet’s Amphitrite Point Lighthouse on Thursday, Jan.… Continue reading

WestJet appeals lost bid to scrap harassment lawsuit

Airline argues judge was wrong to have dismissed the company’s application to strike the legal action

Can U.S. border guards search your phone? Yes, and here’s how

Secretary of homeland security explains a new policy that let’s border guards check phones

‘Beautiful writer’ Nancy Richler dies of cancer in Vancouver hospital

Montreal-born author spent most of her adult life in B.C. as a fiction writer and novelist

Jury convicts spear-wielding Duncan man in 2015 Ladysmith RV park murder

Trever George Meers used a handmade spear to stab Rayna Johnson at the Campers Corners RV Park

Students frustrated by UBCO response to harassment allegations

Students on the Kelowna campus were unaware of resources and worried about lack of communication

Opinion: Dare to be smarter

Just say no works for more than just substance abuse

‘Sing Me a Song’ about B.C. for a chance at $1,000 contest prize

Entries due by March 30 for lieutenant-governor’s British Columbia-themed competition

Facing reality of death, B.C. man learns real meaning of life

Even while preparing for the end, something inside Keven Drews won’t let him stop living

Most Read