Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Grassfire threatens Sooke home

Quick action by local firefighters quickly extinguished flames

Tomato planting controversy inspires Victoria author’s book on transforming cities

Woman behind the Collinson street mural pens third book

Victoria Humane Society needs volunteers after flood of puppies and kittens

Pregnant cats, dogs and their litters are in need of foster care

Stem cell donor with rare genetic makeup needed to save Saanich man after cancer returns

Jeremy Chow is half Canton Chinese, half British and needs a donor with a similar ethnic background

Disney Plus to launch in Canada in November

Analysts say latest streaming service may escalate cord cutting

Sooke’s Old-Fashioned Country Picnic set for Saturday

The free event combines music, kids activities, food and fun

B.C. manhunt suspects left cellphone video before they died: family

Family member says Kam McLeod, Bryer Schmegelsky recorded final wishes

Okanagan bus driver assaulted for asking patron not to smoke

59-year-old in hospital with non-life threatening injuries

B.C. sets rules for ride hailing, same minimum fee as taxis

Larger operating areas seen as threat by cab companies

Two hiking families team up to extinguish fire in B.C. backcountry

Children and their parents worked for three hours to ensure safety of the popular hiking region

Police seek tips in 2015 death of Island teen Brown

Four years has passed since the body of Penelakut Island woman was discovered

Vancouver man arrested after pregnant woman’s SUV stolen, then crashed

Police are recommending charges against a 22-year-old Vancouver man

Most Read