Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Sooke Mounties still searching for suspect weeks after sexual assault

RCMP have been unable to identify any suspects

Saanich ranked third for participation in FortisBC energy-efficient upgrades program

800 older apartment buildings in B.C. have received upgrades since 2015

Provincial funding allows Greater Victoria immigrants, refugees better access to counselling services

The Vancouver Island Counselling Centre for Immigrants and Refugees was a recipient of new funds

Oak Bay hydro box wrap captures community history

Image shows what early homestead on The Avenue looked like

Jagmeet Singh says he’ll vote against throne speech if NDP requests not met

Singh is to meet with Prime Minister Justin Trudeau on Thursday

Community uses loophole to paint 16 rainbow crosswalks after B.C. council says no

So far 11 rainbows are painted and five planned, all since council denied the first proposal in September

Workers’ camp at LNG facility in Kitimat takes shape

Extensive worker camp now being assembled

Former B.C. youth pastor guilty on one of five sexual assault allegations

Judge cites reasonable doubt in finding Cloverdale couple not guilty of majority of charges

238 and counting: Vancouver gelato shop sets Guinness World record for most flavours

Vince Misceo has come up with 588 different flavours over the decades

Killer who fled to Taiwan day after shooting B.C. man over $80 sentenced 13 years later

The sentence comes 13 years after Shaoxin Zhang, 19, was killed in a Burnaby parking lot

B.C. forest industry trade mission finding new markets in China

Diplomatic tensions eased, minister Doug Donaldson says

Most Read