Sidney’s new fire hall keeps getting more expensive

Construction bids continue to exceed initial $10 million budget

Eight more contracts have come before the Town of Sidney in the ongoing construction of its new community safety building — and costs have increased again.

The project is now estimated to cost the municipality $14.5 million — and increase of half a million dollars over the last staff report to council. That earlier report saw the cost of the community safety building jump from $10 million to $14 million.

The reasons remain the same, according to Town staff. Demands upon the construction industry in the region have pushed costs up and fewer overall bidders on components of the project means the Town has less choice.

For example, there were three bidders on the electrical systems in the new structure. Sidney, through its project management firm Kinetic, received three bids, at $1.5m, $1.4m and $940,000. The low bidder, who the Town eventually chose, was Thomis Electric Ltd. and was still close to $290,000 over the Town’s budget.

Of the eight contract areas, only one came in with a bid that was under budget — an $84,000 savings for masonry work. That bid, however, was not selected by the Town. The bid that was approved Nov. 27 came in $38,000 over budget.

The Town has been working with Kinetic to find cost savings within the project and reporter Nov. 27 that they have trimmed $500,000 from originally tendered bids. Of that, $130,000 has been removed from the mechanical component of the project — which staff say is the single largest component, has received only one bidder, and has not yet been finalized. Staff reported that the cost here is already exceeding their budget, but do not expect the total project cost to exceed the $14.5 million estimate.

A staff report says, however, that planned municipal borrowing, as a result of the savings, will increase by only $300,000 — still within the range of borrowing already approved by council. All told, the estimated borrowing impact on Sidney taxpayers will be an average of $48 per yer, or $4 per month.

Councillor Peter Wainwright says, like previous tenders for the community safety building, bids came in over expected amount.

“Staff and contract managers went through a process to bring down costs as much as possible,” he explained, adding however that most tenders still only have one bidder.

“Only one bid in one tender package was lower than budgeted amount,” he added. “This getting pretty close to the end of the project, so staff are optimistic this is going to stay within control.”

Wainwright added the construction market is what it is, and tenders are typically coming in over budget across the board in the Capital Regional District, not just in Sidney.

The community safety building is currently under construction south of the Mary Winspear Centre, next to the Pat Bay Highway. It will be the new home of the Sidney Fire Department and B.C. Ambulance Service.

The Town of Sidney is currently looking for bids to purchase the old fire hall property and the adjacent parking lot. They conservatively estimate getting $3.5 million for the land, money that will help offset the total cost of the new building.



editor@peninsulanewsreview.com

Like us on Facebook and follow us on Twitter

Just Posted

TONIGHT: bartenders compete in Victoria for top title

The Complete Bartender Competition is coming to the Little Jumbo Restaurant and Bar

Squirrels star of guided walk in Saanich park

Going Squirrelly Guided Walk happening Sunday in Francis/King Regional Park

Victoria ranks 20th among 25 Canadian cities for Internet experience

Findings appear in a 2016 report from Canadian Internet Registration Authority

Oak Bay realtor recalls sale of home where family was murdered

Home sellers not always required to disclose violent crimes

Saanich strikes standing committee to help create citizens’ assembly

Membership includes vocal amalgamation critic Coun. Judy Brownoff

Trudeau says politicians shouldn’t prey on Canadians’ fears

The Prime Minister was speaking at a townhall in Ontario

‘I never said there was no collusion,’ Trump lawyer says

President Donald Trump’s lawyer Rudy Giuliani says he has ‘never said there was no collusion’

Body of Canadian miner found after African kidnapping

Kirk Woodman’s body was discovered 100 kilometres from the site where he worked for Progress Mineral Mining Company in Burkina Faso

Study finds more than half of food produced in Canada wasted

The study released Thursday is the world’s first to measure food waste using data from industry and other sources instead of estimates

Snowed-in Austrian nuns insist they’re staying put

Authorities have deployed heavy equipment to clear snow and fallen trees blocking the road to the monastery

Chiasson nets shootout winner as Oilers edge Canucks 3-2

Edmonton moves one point ahead of Vancouver

B.C. chief says they didn’t give up rights for gas pipeline to be built

Hereditary chief: no elected band council or Crown authority has jurisdiction over Wet’suwet’en land

Thieves steal thousands from 140 Coast Capital Savings members

Online fraud tactics included phising and ‘brute force’ in November and December

Condo rental bans may be on way out with B.C. empty home tax

Many exemptions to tax, but annual declarations required

Most Read