Liberals’ 2-year infrastructure plan set to take 5: documents

Government says 793 projects totalling $1.8 billion in federal funds have been granted extensions

Late last year, officials warned that a federal spending spree to repair crumbling roads and water systems could take three years longer than expected to complete, based on internal documents outlining issues with the first tranche of cash in the federal government’s infrastructure program.

The federal government had originally hoped to have cities and provinces complete $5.4 billion in transit and water system work by this March, but quickly realized that more time was needed.

A “secret” fall briefing note to Infrastructure Minister Amarjeet Sohi, obtained by The Canadian Press through the Access to Information Act, says delays hampered a large number of construction projects, requiring that the deadline be extended as far as March 2021.

The heavily blacked-out document predicted the majority of water and transit projects “would require extensions not only for a third year, but beyond into a fourth year (i.e. 2019-20) and fifth year (i.e. 2020-21),” referencing the federal fiscal years in brackets.

Sohi agreed to a blanket deadline extension to March 2020, turning what was to be a two-year stimulus program into a four-year plan.

He said the decision to grant extra time to 2020, instead of 2021, was based on the expected cash flow for projects and the ability for construction companies to handle all the extra work.

“This is not about that projects are being delayed, it’s about taking a little longer to complete those projects or taking a little longer to have the buses manufactured because of construction and manufacturing capacity,” Sohi said in an interview from Edmonton.

“From our perspective, we made a commitment to build and rebuild infrastructure and focus on the repairs in phase 1 and … we are achieving the results we intended to achieve, but we also want to give flexibility.”

As of Friday, the federal government had approved more than 3,400 water and transit projects with a combined federal contribution valued at almost $4.2 billion. Of that money, federal coffers had only doled out about $175.6 million to date, based on figures available on the Infrastructure Canada website.

Federal dollars flow once cities and provinces submit receipts for reimbursement, often creating a lag between when work takes place and when the federal money is spent.

In some cases, the federal government won’t receive receipts until a project is completely done. In other cases, projects are delayed because of labour strife, bad weather or other factors beyond Ottawa’s control.

The government says 793 projects representing about $1.8 billion in federal contributions have been granted individual extensions from Sohi. Between those extensions, and delays in filing expense claims, federal officials last year decided to shift more than $2 billion in planned spending to future years.

Provincial and municipal officials say that the time needed to go through the funding approval process contributed to the delays.

Having officials vet the details of each proposal before getting federal approval for funding meant some cities put off breaking ground until they knew federal funding would come their way.

“We heard loud and clear from some municipalities that they were struggling to meet two pieces of criteria: timeline requirements and a provision that would require municipalities to incur 60 per cent of their costs by March 31st, 2018,” said Alex Benac, a spokesman for Ontario Infrastructure Minister Bob Chiarelli.

The extra time and removal of the local spending requirement, which Chiarelli asked for in September, has given cities “much-needed time to get shovels in the ground and keep their projects on track according to a more generous, achievable timeline,” Benac said.

Federal and provincial officials say the lessons learned from the first phase of the program will be used in designing the second phase.

Both sides want funding agreements for the second, longer and more lucrative phase of infrastructure spending signed by March.

Jordan Press, The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

‘Blue Monday’ isn’t real, but depression can be

CMHA encourages people to prioritize their mental health

Sooke Potholes viewing area likely to remain closed

Report says that more rockslides likely in the area

Residents push back on downtown Victoria tree removal

The birch tree at the Wharf-Government intersection will be removed to make way for bike lanes

Toronto Arrows players take aim at youth rugby clinic

Juan de Fuca team offers get acquainted clinics

Husband of slain RCMP officer ‘disgusted and disheartened’ by parole board

Killer of Const. Sarah Beckett allowed limited day parole for alcohol treatment

UPDATE: B.C. legislature managers accused of excessive travel, personal expense claims

Clerk Craig James, security chief Gary Lenz call allegations ‘completely false’

B.C. man fined $10,000 after leaving moose to suffer before death

Surrey man was convicted last week on three Wildlife Act charges

Anti-pipeline group wants NEB to consider impact of emissions, climate change

Stand.earth filed NEB motion asking to apply same standard to the project as it did with Energy East pipeline

B.C. man charged in 2014 snake venom death of toddler

Henry Thomas was taking care of the North Vancouver girl the day before she died

B.C.’s largest public-sector union wants inquiry into money laundering, drugs

Union officials say Premier John Horgan and Attorney General David Eby have not ruled out the possibility of a public inquiry

Teen in confrontation with Native American: I didn’t provoke

Nick Sandmann of Covington Catholic High School said he was trying to defuse the situation

Suspect allegedly armed with handgun robs Island gas station

Incident occurred Sunday night in Nanaimo

MARS seeing influx of sick, injured eagles from north part of Vancouver Island

Factors for increase in eagle cases can be anything from lead poisoning to vehicle strikes

Kamala Harris opens U.S. presidential bid in challenge to Trump

The 54-year old portrayed herself as a fighter for justice, decency and equality in a video distributed by her campaign

Most Read