Anti-smart meter protester Sharon Noble greets delegates at B.C.'s 2012 municipal convention in downtown Vancouver. Wireless meters have been blamed for bee deaths

B.C. smart meters cleared in Ontario debacle

$1 billion over budget, Ontario tried to use smart grid to shift load to off-peak hours. It hasn't worked

Ontario has become notorious for bad energy policy decisions, from leaky nuclear plants and brownouts, to a costly green energy subsidy deal with Samsung, to a pair of hastily cancelled gas-fired power plants that helped push former premier Dalton McGuinty from office.

So it was no surprise to weary Ontario electricity ratepayers when Auditor General Bonnie Lysyk wrapped up 2014 with a report condemning the province’s wireless smart meter program for a $1 billion cost overrun and failure to reach the program’s goal of reducing power consumption.

Unlike BC Hydro’s wireless meter program, Ontario used the smart grid’s real-time consumption data to offer discounts for off-peak power consumption, hoping to ease the load on its outdated power grid while giving customers some relief from soaring rates. But few embraced the incentive to run their clothes dryers late at night to save money.

Diehard smart meter opponents in B.C. jumped at the bad news from Ontario. Their theories of sudden billing surges, vague health concerns and even smart meter surveillance have all been debunked, but here they had a credible voice saying they are a waste of money.

Alas for them, Lysyk held up B.C.’s smart meter program as the model Ontario should have followed.

The Ontario government “did not complete any cost-benefit analysis or business case prior to making the decision to mandate the installation of smart meters,” the auditor wrote. “This is in contrast to other jurisdictions, including British Columbia, Germany, Britain and Australia, all of which assessed the cost-effectiveness and feasibility of their smart metering programs.”

Lysyk’s report also noted BC Hydro developed its business case in 2006, updated it in 2010 as meter technology evolved, and implemented it in 2011 with a plan to recover costs over 20 years. BC Hydro’s savings come mainly from reduced electricity theft, faster location of power outages and more accurate load management.

B.C. also responded to the anti-smart meter holdouts with an optional fee to cover manual meter readings for those who insisted the cellphone-like data transmissions are a threat to their health.

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

Laid-off hotel workers demanding the right to return to work at Victoria protest

Businesses in accommodation and food sector report laying off 80 per cent of workforce

Canadians with disabilities disproportionately hit by COVID-19 pandemic

More than four out of 10 British Columbians aged 70 and up have various disabilities

Sooke homeless camp to stay until a solution is found

To forbid Ed Macgregor camp would go against Canadian Charter of Rights and Freedoms

Police issue warning after baby comes across suspected drugs in Kamloops park

The 11-month-old girl’s mother posted photos on social media showing a small plastic bag containing a purple substance

Collision results in train derailment just east of Golden

The derailment occurred Sunday night, according to a statement from CP

Lower Mainland woman says llama farming neighbour shot her 11-month-old pup

Young dog was on owner’s Maple Ridge property when it was killed on June 21

B.C. records 31 new cases, six deaths over three days due to COVID-19

There are 166 active cases in B.C., 16 people in hospital

B.C. highway widening job reduced, costs still up $61 million

Union-only project scales back work to widen Trans-Canada

BC Wildfire Service to conduct night vision trials for helicopters in South Okanagan

This technology could assist with future firefighting operations

Victoria man dies after skydiving incident on Vancouver Island

34-year-old had made more than 1,000 jumps

Most Read