The balustrade replacement atop the seawall will follow on the heels of the seawall repair.

Repairs overdue on 100-year-old Dallas Road seawall

Project completion pushed into 2019, extra $895,000 budgeted for rehab work

It’s been more than 100 years since the seawall along Dallas Road was constructed and since that time, it has been battered by the crashing waves from countless storms.

Despite its strength, it’s time for the seawall to get some help. Repair work actually started in 2012 when it was determined that parts of the structure were in serious decline. It continued in 2014 and the projection was for the entire project to be completed by 2016.

But as sections of the wall were opened up, it became clear that the deterioration in the structure was more serious than originally suspected, said City spokesperson Rebecca Penz.

The project has now been extended into 2019 and the City’s latest budget documents show $895,000 is allocated for the work. Despite the poor condition of the wall there are no plans to replace the aging structure, Penz noted.

“Instead it will receive a face lift that involves the stripping away of rotting steel and concrete. The wall is then re-faced with a reinforced concrete panel that is tied into the back part of the old wall.”

Sections of the wall that have been refaced in this manner are visible in the area of Oswego Street where work stopped in 2017.

When complete, the project will deliver a structurally sound seawall that protects the existing road, sidewalk and underground utilities on the affected section of Dallas Road, a section that stretches from the Breakwater parking area to the far east portion of the wall at Lewis Street.

Investigation of the seawall structure have also revealed that repairs are urgently required to the balustrade atop the seawall.

“The existing balustrade is failing and has been bolted to hold portions together,” read the budget report on the project. It went on to say the structure has been painted every two years to reduce rust stains, but a replacement balustrade must be designed and approved. The final design and cost estimates for that portion of the project still require council approval.

All the work on the balustrade, once approved, will still have to be done in conjunction and co-ordination with the CRD’s work on Dallas Road for sewage treatment conveyance piping.

To further complicate the issue, any work on the seawall and balustrade has to take place outside of the region’s winter storm months.

“They have to pull out during the storm months for safety reasons,” explained Penz.

editor@vicnews.com

Just Posted

Esquimalt man faces four charges of sexual assault, investigators suspect more victims

71-year old Kit Wong practiced acupuncture from his home during the time of the assaults

Heat and smoke raises health risks

Rick Stiebel - Sooke News Mirror Health risks arising from heat and… Continue reading

Sooke fire chief in right place at right time

Second bin fire this year a concern

Pet-A-Palooza a good reason to ‘pawse’ this weekend in Victoria

Puppies, goats, wiener dog races and more on the grounds of St. Ann’s Academy Aug. 18-19

B.C. declares state of emergency as more than 560 wildfires rage

This is only the fourth state of emergency ever issued during a fire season

Interim GoFundMe payments approved in Humboldt Broncos crash

$50,000 to be given to each of the 13 survivors and each family of the 16 people who died

Altidore nets 3 as Toronto drubs Whitecaps 5-2

Vancouver falls 7-4 on aggregate in Canadian Championship final

Ottawa intervenes to get B.C. ball player, 13, to Little League World Series

Before immigration issue was resolved, Dio Gama was out practicing the game he loves Wednesday

Pet goldfish invades small B.C. lake

Pinecrest Lake is located between Whistler and Squamish

Mounties deployed to help B.C. communities affected by wildfires

RCMP officers heading to places particularly within central, northern and southern B.C.

Quebec sets aside $900 million for companies hurt by U.S. tariffs

Premier Philippe Couillard says his government will make $863 million available over five years

B.C. company patents Sasquatch, the country’s first homegrown hops plant

Created by Hops Connect, Sasquatch hops are being grown commercially for the first time in B.C.

Farmers ponder impact of alternatives to pesticides being banned

The nicotine-based pesticides scientists have linked to a rising number of honey bee deaths will be phased out of use in Canada over a three year period starting in 2021.

Most Read