Vancouver Island school upgrade $1.4 million over budget and no one noticed

The original construction budget was not adjusted to account for some expenses

Following the completion of the Georges P. Vanier seismic upgrades in October, the school district determined they had gone approximately $1,450,000 over budget.

The $33.1 million upgrade project started in 2016 and was completed in phases, including adding additional classrooms, specialized spaces such as a new auditorium and an Aboriginal education room, and relocating the library. The project also included upgrading the school’s mechanical and electrical systems that were nearly 50-years-old. Approximately $32.8 million for the project was provided by the Ministry of Education and around $1 million was from the school district.

According to SD71 secretary-treasurer Nicole Bittante, the school district did not realize they were over budget until the project was completed as they thought all expenditures had been accounted for.

“While this overspend was not identified until the project was completed, it was thought all along that the budget allowed for these expenditures,” said Bittante. “District staff were reconciling all of their amounts to the original budget. In the meantime, the original budget hadn’t been adjusted for various items. So it appeared during the term of the project that the project was on schedule and on budget.”

Bittante outlined the areas where the overspending happened, with the most significant portion being the GST.

“The original construction budget back in 2015 that was provided to the construction company did not include GST, however, the budget should have included the non-rebatable portion of GST,” she said. “There’s a portion that the district pays and then receives back in a rebate.”

The non-rebatable portion of GST was a cost to the district of approximately $477,000.

Other areas where there was overspending included a portion of the director of operations’ salary and some wages for a custodian which were not reduced from the construction budget, totaling $196,000.

In 2017, the gymnasium walls required repairs due to a safety concern, and while the Ministry provided $220,000 to address the issue, the fix still went $117,000 over budget.

The costs for the initial project planning, totaling approximately $152,000, were also not removed from the construction budget. Another $40,000 was listed as “other balancing factors,” and the project went an additional $465,000 over budget as this amount was not covered by the risk reserve.

“The $33 million included a $4 million risk reserve. It wasn’t guaranteed funding, it was an amount that was awarded through the ministry, but it was an amount that we had to apply for and there were criteria attached to it,” said Bittante. “I think the issue is that we, in our budget, gave the $4 million to the construction company and it was spent.”

The school district was only able to access approximately $3.5 million of the $4 million with the rest being a cost to the district.

Bittante clarified that the overspending was not a reflection of the contractor as they came in on budget. Their budget just should have been smaller.

“They came in on target with money that they were given, but we weren’t able to access all the funds.”

She adds that increased oversight will occur on all future capital projects to ensure any overspending is identified and taken care of immediately.

At Tuesday’s meeting, the SD71 school board voted in favour of transferring $1,450,000 of unrestricted operating surplus to cover the overspend.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Woman arrested for hit and run that left another vehicle in Colwood front lawn

The woman was issued a 24 hour driving prohibition and a ticket

Sooke jumps on board to ban use of rat poison

City staff will educate residents on harmful effects of rodenticides

VicPD looking for 17-year-old girl, believed to be in downtown Victoria

Circumstance under which she has gone missing are considered to be high-risk

New urgent, primary care health centre opens in Saanich come November

North Quadra area facility to provide same-day, ongoing care for folks without family doctors

McKenzie interchange project drives towards completion

Motorists asked to continue following construction zone signage as crews will be on site into the fall

VIDEO: B.C. to launch mouth-rinse COVID-19 test for kids

Test involves swishing and gargling saline in mouth and no deep-nasal swab

70-year-old punched in the head in dispute over disability parking space in Nanaimo

Senior’s turban knocked off in incident at mall parking lot

One person dead in two-vehicle accident in North Island

Highway 19A was closed for several hours north of Courtenay following the crash

CHARTS: Beyond Metro Vancouver, COVID-19 cases in B.C. haven’t increased much recently

COVID-19 case counts outside of Metro Vancouver have been level since July

Record-breaking 165 new COVID-19 cases diagnosed in B.C. in 24-hour period

Fifty-seven people are in hospital battling the novel coronavirus

B.C. teachers file Labour Relations Board application over COVID-19 classroom concerns

The application comes as B.C.’s second week of the new school year comes to a close

Young Canadians have curtailed vaping during pandemic, survey finds

The survey funded by Heart & Stroke also found the decrease in vaping frequency is most notable in British Columbia and Ontario

Long-term care need pressuring acute care in Comox Valley, Strathcona

Region could use a couple of large facilities for seniors on the north part of the Island

B.C.’s COVID-19 economic recovery plan: Top 5 things you need to know

Jobs training, tax incentives for employers to hire staff and more

Most Read